The

VALLEY GREEN

Inn

 

 

Home ] Up ]

Picture 002.jpg (156707 bytes)

Cast iron underground piping being installed.. This time consuming process took nearly three weeks to complete.

Picture 043.jpg (146874 bytes)

Stone work which will lay beneath the entire slab ready for concrete to be poured.

Picture 048.jpg (160278 bytes)

1st section of floor framed out.  Note metal box in by wall... this is a greasetrap to ensure oil, grease, etc... does not flow back into the sewer system.

Picture 052.jpg (157687 bytes)

Pouring concrete into molds.  The wood will be removed during and after the concrete sets. Picture 056.jpg (157166 bytes)

Looking at the new terrace area.  Stone removed from the project will be used to "face" the wall to continue the look of the existing stone wall

Picture 070.jpg (147355 bytes)

Stone foundation atop concrete footers.  Almost ready to be framed and poured.   Half the floor is in place.